Energy Link is the Thunder communication link used between compatible Thunder devices. It carries both 54 VDC power and network communication over the same two conductors (ELL and ELH), allowing power and data to share a single twisted pair.
How Energy Link Works
Energy Link uses the ELL and ELH conductors to carry both 54 VDC power and network communication between Thunder devices. A shield connection is also used where specified by the product wiring diagram.
Energy Link Connections
|
Connection |
Description |
|---|---|
|
ELH |
Energy Link High |
|
ELL |
Energy Link Low |
|
Shield |
Connect the cable shield to the Shield terminal when required by the product wiring diagram. |
Cabling Requirements
|
Parameter |
Requirement |
|---|---|
|
Voltage |
54 VDC |
|
Cable |
Single twisted pair |
|
Wire gauge |
18 or 20 AWG, depending on the connected product specification |
|
Maximum distance |
1000 m (3280 ft) |
|
Shield |
Connect where indicated by the product wiring diagram |
Where Energy Link Is Used
Energy Link is used to connect Thunder cabin phones to the Thunder system.
-
Low-Rise systems: TG1132 and TG1164 supervisors provide Energy Link ports for the Thunder cabin phones.
-
High-Rise systems: The TP1002 connects to TG1232 and TG1264 gateways through Energy Link. Each gateway then provides Cabin connections for the Thunder cabin phones using ELL, ELH, and Shield.
For complete system wiring, refer to the installation documentation for the applicable Thunder architecture.